5
votes
1answer
133 views

Scheduling with transition costs - DOCPLEX

I am dealing with a kind of scheduling problem. I have a set of tasks to be executed by a set of machines. It is known that different machines are able to execute the same task, but each machine can ...
7
votes
2answers
177 views

CPLEX CP Optimizer Java API function missing

I can not seem to find the needed functions to model the following problem through the Java API (CP Optimizer): a machine that has downtime and sequence-dependent setup times, with the extra ...
9
votes
1answer
152 views

How to tackle large nurse scheduling problem?

I have a nurse-scheduling type of problem with a time span of a year and many employees. Formulation My main variables are: \begin{align}x_{e,t} &= \begin{cases}1 \text{ if employee } e \text{ ...
9
votes
2answers
415 views

What is the difference between job shop scheduling and resource constrained project scheduling?

I read here https://slideplayer.com/slide/3353960/ that RCPS is a generalized version of job shop scheduling. I'm new to this area and I'm trying to classify a specific variation of these types of ...
6
votes
3answers
113 views

Trouble with scheduling problem assumptions

Reading the famous book by Pinedo, I came across : Usually, the subscript $j$ refers to a job while the subscript $i$ refers to a machine. If a job requires a number of processing steps or ...
8
votes
1answer
128 views

Extract info from Gurobi binary variables during run-time

Actually the question below is not specific to Gurobi, but that's the tool I am using. Consider a scheduling problem where a 2D array of binary variables $Z(i,v)$ is defined, where $i$ is index of ...
8
votes
3answers
621 views

Maximize assigned tasks to each worker

In a scheduling problem I want to assign the maximum number of tasks to one worker before assigning it to another. For example, if I have $10$ tasks and $2$ workers, the best assignment would be $(10, ...
4
votes
1answer
213 views

XOR constraint representation

In an scheduling optimization problem, for job $l$, $\xi_l$ is binary variable that $\xi_l=1$ shows job $l$ is selected. $t_{r,l}$ and $t_{e,l}$ are registration time and time that job is completed. ...
4
votes
1answer
218 views

Scheduling Optimization Problem

I want to solve below optimization problem. This is scheduling problem where I seek to complete as many of the jobs $\xi_l$ (objective function and constraint 1), with $T_C$ being the last time until ...
12
votes
3answers
1k views

Number of aircraft to operate in an airline company

Suppose that an airline company has X planes, in general the companies keep a number of these aircraft (say 80% of X) in reserve in case of hazards. My question is how the airline companies compute ...
7
votes
2answers
570 views

Finding an Objective Function for Assigning Employees to Sequence Dates

I am using a mixed-integer-program to schedule employees to projects. These projects can have a time window to get completed from a few weeks to a few months. At the moment I am working in a ...
9
votes
1answer
98 views

How to model 24 hours demand into a daily shift schedule?

I am working on a weekly staff scheduling optimization problem with 24/7 demand. The binary decision variable is: $X_{\text{staff},\,\text{day},\,\text{shift}}$ whether to assign the staff $s$ to day ...
8
votes
1answer
118 views

Workforce Scheduling problem - Modelling to minimize resources

I am working on a scheduling program for a service desk. I want to decide the number of people required to come in at each shift. The data I have is: There are 4 overlapping shifts Arrival pattern at ...
16
votes
4answers
794 views

Best model for precedence constraints within scheduling problem

Suppose I'm modeling a problem where I want to compute the start time bucket for some jobs. All time buckets have equal duration. There are some additional constraints involved but I also have to ...
10
votes
1answer
179 views

Algorithm for workforce scheduling for call volumes

I am trying to solve a workforce scheduling and optimization problem. Available data: daily level forecasted call volumes, shift schedules, resource utilization at the aggregate level, AHT at ...
8
votes
1answer
102 views

What class of scheduling problem models jobs which require multiple machines simultaneously?

In the Flow/Job Shop problems, and other related scheduling problems, a common assumption is that at any given time, a particular job will be being processed on at most one machine (usually... none). ...
8
votes
1answer
392 views

Finding minimum time for vehicle to reach to its destination

Given a set of Vehicles with source and destination I need to find the minimum time of travel for all the vehicles, there are also some charging stations and its necessary for vehicles to charge 1 ...
9
votes
2answers
320 views

What is this type of scheduling problem called?

I am currently working on software that deals with a specific type of scheduling problem, and I want to improve the scheduling algorithms that it uses. However, when I tried to research algorithms ...
8
votes
0answers
81 views

Examples for a kind of “set family hitting” problem

Given a ground set, say $[n]=\{1,2,\dots,n\}$, and a collection of subset families $\mathcal F_i\subseteq 2^{[n]}$, $i=1,2,\dots,m$, I want to select $m$ sets $B_i\in\mathcal F_i$ such that the ...
12
votes
3answers
799 views

How to model a mixed-integer linear programming formulation in Python using Gurobi?

I can remember that I spent some time in understanding how to formulate my first model. So I aimed at presenting a complete model here, wishing to save some time for students or researchers needing it....
10
votes
5answers
357 views

Dealing with non-overlapping constraints

Let us consider the following problem: Let $T$ be a set of tasks. Each task $t \in T$ has a duration $d_t$ and a target start time $s_t$. No two tasks can be executed in parallel. The objective is to ...