2 votes
2 answers
158 views

OR-Tools CP-SAT solver: is it possible to name a constraint like in GUROBI

I try to implement cp model with OR-tools CP-SAT solver. Please, is it possible to name constraints for being able to manage conflict later like for variables: ...
Issouf's user avatar
  • 53
1 vote
0 answers
57 views

How to cmpute IIS using the Or-Tools solver?

I'm trying to solve a MIP using Google Or-Tools, but it's showing that the model is infeasible. I'd like to know if there is a convenient way to analyze which constraint or variable bounds are causing ...
Ying's user avatar
  • 69
1 vote
1 answer
37 views

Output a readable model file and control the solver parameters in Or-Tools

I am using Java to call the API of or-tools in IntelliJ IDEA to solve a mixed-integer programming problem. There are some modeling statements such as ...
Ying's user avatar
  • 69
-1 votes
0 answers
50 views

Machine-state constraints for jobshop problem

Problem outline I am trying to implement a job-shop problem using OR-Tools, which can be framed as a typical job-shop problem (minimize overall maketime of machines performing tasks) but the ...
Patrick Bardsley's user avatar
1 vote
1 answer
68 views

Non integer linear objective in or-tools CP-SAT

It seems that or-tools' CP-SAT solvers allows for non-integer coefficients in a linear objective expression. Am I correct, or is it just that the solver doesn't check for integrity and rounds the ...
E. Fischer's user avatar
1 vote
1 answer
67 views

Scheduling repeated tasks with minimum duty cycles

Several tasks need to run repeatedly in a channel, one at a time, over a repeating time frame of length $T$. Associated to each task $i$ is the duration $L_i$ the task will take to run, and a maximum ...
Mark's user avatar
  • 111
0 votes
2 answers
60 views

Formulating assignment problem with people attributes that need to be balanced per assignment attribute in or-tools, CP-sat

I'm trying to do an assignment problem with the following characteristics: I have two sets that need to be matched with each other, set A (Students) and set B (Class combinations). Set A and B have ...
Riezz's user avatar
  • 21
0 votes
1 answer
88 views

Using binary variable or integer variable in Constraint Programming (CP)?

I am trying to solve an assignment problem by Constraint Programming (CP). Let us consider a task assignment problem that have $|M|$ tasks and $|N|$ machines, each task has different processing time ...
Penghui Guo's user avatar
3 votes
0 answers
40 views

Adding synchronisation constraint in Prize-collecting VRPTW

I am solving a Prize Collecting VRPTW. In my problem, each node represents a visit that needs to be made within a certain time window, and the "prize" for each node is the time spent at the ...
orman's user avatar
  • 33
0 votes
1 answer
103 views

Team Orienteering Problem with Time Windows infeasible using CP-SAT solver in Google OR-Tool

I am developing a TOPTW where there are a set of N nodes. Each node i is associated with a visit time, which is also the score Si. The starting point and the end point of each tour is fixed, which is ...
orman's user avatar
  • 33
0 votes
1 answer
74 views

Are there any hidden differences in OR-Tools' default parameters for a MIP model in Python vs C++?

or-tools-discuss cross post here. As a disclaimer -- I am very aware that OR-Tools' Python code are just wrappers around their C++ source code. I'm just getting an odd discrepancy between a model ...
gjgutier545's user avatar
0 votes
2 answers
94 views

TSP problem using Google's OR tools

This is the Travelling Salesperson Problem code from Google's OR tools. I used a simple instance that is defined in the data dictionary and has optimal value (sum of Euclidean distances) of 36.26 for ...
Andrew's user avatar
  • 143
0 votes
1 answer
81 views

how the number of employees affects the married employee scheduling problem

My scheduling problem has a specific pattern of 2 days of work followed by 2 days off. Additionally, there is a week off after every 4 weeks of work. The scheduling matrix (P) has five different ...
abdula smith's user avatar
1 vote
1 answer
94 views

Routing problem - How can I make use of the Clarke and Wright algorithm for a CVRP, when using the ortools library?

TL;DR: How can I specify to ortools to use only the Clarke and Wright algorithm. Hello, I'm trying to solve a CVRP. When exploring the my options, I stumble by the ortools library, it gets the job ...
user.mokho's user avatar
3 votes
2 answers
115 views

how to count the number of values that are greater than zero in OR-Tools

I am using OR-Tools for an employees scheduling problem. I have a dictionary that is defined as an IntVar, where such dictionary contains the number of hours that will be assigned to each employee, ...
luca_dix's user avatar
2 votes
3 answers
104 views

Constraint programming problem with matrix of integers

I am trying to solve the following problem. Suppose $A$ is an $m \times n$ matrix of integers with entries in $\{1, \dots, k\}$. There are two kinds of constraints on the entries of this matrix: For ...
TheProofIsTrivium's user avatar
2 votes
1 answer
548 views

What exactly does the AddHint() method in Google OR-Tools' CP-SAT solver do?

I have an optimization problem that I am solving with CP-SAT and I am using the Python interface. Moreover, I know a good feasible solution coming from a heuristic and I want the solver to start its ...
John D's user avatar
  • 199
-1 votes
1 answer
172 views

[OR-Tools][CP-SAT] Implement an indicator function in a constraint

Good morning ! I would like to implement this constraint using CP-SAT (see image below). x_i,j is a boolean variable, a and b are given. The problem is that I don't know how to implement the ...
Arthursbr's user avatar
1 vote
1 answer
343 views

About circuit constraints in OR - tools

I am trying to implement a scheduling problem to solve with CP-SAT from OR-tools. There, in particular, for every machine I want to add a time transition constraint from every task that is performed ...
John D's user avatar
  • 199
3 votes
1 answer
123 views

CP-SAT's `NumBooleans()` parameter

The solver API for CP-SAT offers the attribute NumBooleans, which is documented as "Returns the number of boolean variables managed by the SAT solver". ...
Hanno's user avatar
  • 181
1 vote
2 answers
101 views

Alternative Approaches to Assignment Problem

I have a real world use case where I aim to optimize the assignment of trucks to orders of different sizes over a time window by minimizing some cost function (e.g. total distance traveled). The below ...
Jordan C's user avatar
4 votes
1 answer
270 views

Relevance of order of model construction in CP-SAT

Question 1: Is ortool's CP-SAT sensitive to the order in which a model is constructed? In other words, does it matter which variables and constraints come first? I am seeing a high performance ...
Hanno's user avatar
  • 181
1 vote
1 answer
69 views

Multiplicity-Constraint in Constraint Programming Solvers

I need to solve a CSP with a constraint imposing upper bounds on the multiplicity of variables in a list. More precisely, I need a constraint of the form ...
guigux's user avatar
  • 113
1 vote
1 answer
427 views

OR-Tools: Nonlinear constraints?

I have inherited a reasonably simple ortools-based optimizer (Python) with linear relationships that I need to non-linear-ize, and I have no idea how to do that. The relevant part of my problem looks ...
Matthias Urlichs's user avatar
1 vote
1 answer
567 views

TypeError: unsupported operand type(s) for *: 'IntVar' and 'float' in ortools [closed]

I am trying to implement a constraint as follows: ...
mufassir's user avatar
  • 181
4 votes
0 answers
653 views

Google-OR tools vs Pyomo and other commercial Solvers for solving a simple maximum flow problem

I have implemented a Pyomo model for solving maximum flow problem as a subroutine of an algorithm. However, the approach does not scale very well because Pyomo does not provide a very good way to re-...
Pia MiA's user avatar
  • 392
2 votes
1 answer
104 views

Control load per trip in multi trip VRP in ORTools

I have implemented multitrip VRP in ortools (To be specific, solved CVRPTW with virtual depots). Maximum number of trips per vehicle is limited to 2. I want to put a hard constraint that load carried ...
mufassir's user avatar
  • 181
1 vote
1 answer
174 views

Applying weights to assignment problems for linear MIP solvers

In previous posts, A & B, I posed the Movie Theater Problem. In short, the movie theater problem encompasses assigning viewers to seats such that the distance between viewers is maximized, however,...
jbuddy_13's user avatar
  • 481
2 votes
1 answer
158 views

Google OR Tools: Iterative Assignment Problem

This question is a Google OR-Tools specific implementation of recommendation from a previous question. In short, the movie theater problem encompasses assigning viewers to seats such that the distance ...
jbuddy_13's user avatar
  • 481
2 votes
2 answers
127 views

Mixed Integer Programming: Iterative assignment problem

I have a real world problem, which is analogous to the below toy problem, which I call 'The Movie Theater Problem' (TMTP.) In TMTP, movie viewers are assigned seats which principally balances two ...
jbuddy_13's user avatar
  • 481
3 votes
0 answers
193 views

Or-tools : CVRP multiple time window with multiple location

I am using or-tools to solve a CVRP with multiple time window, and multiple location. Meaning that a customer can move during the day. I can't achieve to add constraint like if i deliver the customer ...
Cyprien's user avatar
  • 31
1 vote
1 answer
114 views

Simple Constraint Programming Problem: docplex works but equivalent ortools model is infeasible

I have a simple constraint programming model which can be solved using the docplex library, however I am struggling to implement the same model using ...
SlowLoris's user avatar
  • 145
5 votes
3 answers
451 views

Maximize the minimal distance between true variables in a list

I'm using the OR-Tools CP-SAT solver on a list of $n$ boolean variables $x_i$. I'm trying to maximize the minimal distance between two true variables in this list, as illustrated by the following ...
Blackhole's user avatar
  • 235
1 vote
1 answer
111 views

(OR-Tools) Custom Function to Evaluate Intermediate Solutons

I have a system with $k$ tasks, where each task is a state in a Markov chain. I am working on allocating agents to each task. I would like to achieve a specific distribution of the agents among these ...
Raghav Thakar's user avatar
2 votes
1 answer
80 views

Circuit constraint leading to infeasibility if there are 0 jobs producable one a machine

Using the CP-SAT Solver: My Model turns infeasible whenever there is no job available for a machine. Not every job can be built on every machine. Example Situtations: Less jobs than machines No jobs ...
cl_cookie's user avatar
3 votes
1 answer
401 views

Google OR-Tools, algorithms under the hood?

Under the hood, what algorithms does Google OR-tools support? From adjacent questions, I saw someone as this question and the answer linked to this repo. However, these sources just show how to use ...
jbuddy_13's user avatar
  • 481
2 votes
1 answer
248 views

Multiple Knapsack with Varying Values

I wish to assign customers to their nearest distribution hubs. These hubs have maximum capacities however, and if these are breached I would like to assign customers to the next most appropriate hub. ...
B Marshall's user avatar
2 votes
1 answer
191 views

RAM overflow when scheduling 1000+ intervals

Due to the answers to this and this questions, I was able to find the optimal solution for scheduling problem. However, if there are many tasks that must be scheduled, e.g. 1000+, then the solver ...
Artem Popov's user avatar
2 votes
1 answer
319 views

CP-SAT solver doesn't use all space available for scheduling

This problem is a continuation of this problem. The issue here is the solver doesn't use the whole space available for the scheduling and thus some jobs are not being scheduled. For example: we need ...
Artem Popov's user avatar
3 votes
1 answer
246 views

Force gaps between tasks, tasks are scheduled within their job's time windows in Jobshop problem

The problem I'm trying to solve is a modification of the original Jobshop problem. The additional constraints are: There is only one machine for all jobs and their tasks. Each job has a priority (...
Artem Popov's user avatar
3 votes
1 answer
300 views

Minimum cost flow problem with multiple arcs between nodes in Python / Google OR

Is it possible to work with multiple arcs between 2 nodes within Google OR? Or are there better modeling techniques? I want to optimize flow from supply to demand areas, where supply and demand are ...
Fabian's user avatar
  • 31
3 votes
0 answers
166 views

Can Pyomo be linked with Google's GLOP or CP-SAT solvers?

Pyomo can be linked with several solvers Open source and commercial ones. I was wondering if Pyomo can be linked with Google's GLOP or CP-SAT solvers?
Optimization team's user avatar
2 votes
1 answer
163 views

Scheduling optimization, Adding 4 day same shift and 3 day off weekly constraint

Am writing a small scheduling program in C# for a group of 7 staff who will be working in three shifts daily for 4 weeks. Am using the google OR-Tools Template, but i have modified it abit This is the ...
indago's user avatar
  • 121
1 vote
1 answer
145 views

Modeling Multi-Agent Collision in Google CP-SAT Solver

I would like to implement a solution for Multi-Agent Pathfinding Problem using Google's CP-SAT Solver. How do I implement the constraint that prohibits 2 or more agents from occupying the same cell at ...
Raghav Thakar's user avatar
1 vote
2 answers
227 views

Google CP-SAT Infeasible ILP for Large Problem Area

I am trying to generate a shortest path between source and sink in a square grid of cells. I am using the Google CP-SAT solver ...
Raghav Thakar's user avatar
6 votes
1 answer
370 views

How to Model Path Being Only Through Adjacent Cells

I am trying to develop a MILP for a path planning problem. I am operating on a grid of cells that represents a map. The arrangement of cells in the grid represents the placement of the cells in real ...
Raghav Thakar's user avatar
0 votes
1 answer
199 views

or-tools: job shop problem never exists not finding additional solutions

I am trying to solve a flexible job shop problem variant using or-tools. And in some input configuration, in general after one month of scheduling time, I am facing a weird behavior. I am aware that ...
Joel's user avatar
  • 9
3 votes
0 answers
451 views

Incorporating OR-Tools in a CMake Project

I'm trying to incorporate or-tools into my cmake project. I've tried some of the suggestions given by the project maintainers, who give a few different ways to integrate or-tools in the readme and in ...
Connor's user avatar
  • 431
5 votes
1 answer
709 views

How does OR-Tools improve on an initial solution to CVRP?

I have an initial solution to a CVRP instance which I am setting as input to the solver. The solver as expected returns an improved solution. I have a few questions regarding the solver. How does the ...
Alphanerd's user avatar
3 votes
0 answers
420 views

Circuit constraints in ortools

I am looking to assign tasks to people. Each successive task should be started after the first one is finished and should be started at the same location as the preceding task. While the time ...