I am looking for an optimization algorithm to minimize the cost of transportation and storage cost in warehouse.
Let's assume the following table gives us the weekly forecast of Demand.
+--------------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+
| | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 |
+--------------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+
| Demand | 2,300 | 1,800 | 1,100 | 2,300 | 2,000 | 1,600 | 2,200 | 2,000 | 2,900 | 1,900 | 2,000 | 1,000 |
| Buffer | 600 | 500 | 300 | 600 | 500 | 400 | 600 | 500 | 800 | 500 | 500 | 300 |
| Total Demand | 2,900 | 2,300 | 1,400 | 2,900 | 2,500 | 2,000 | 2,800 | 2,500 | 3,700 | 2,400 | 2,500 | 1,300 |
+--------------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+---------+
The transportation cost follows the below mentioned price buckets given the ordered amount of units.
+---------------+----------------------+
| Units | Delivery Cost / Unit |
+---------------+----------------------+
| Less than 500 | 50 |
| 500 - 1000 | 40 |
| 1000 - 1500 | 35 |
| 1500 - 2000 | 30 |
| 2000 - 2500 | 25 |
| 2500 - 3000 | 20 |
| 3000 above | 15 |
+---------------+----------------------+
There is fixed 30$ storage cost to maintain inventory in warehouse. Time for delivery of stock from order point is 5 days. So we need to order 5 days prior if a certain quantity is required today.
I am looking for an algorithm that would help minimize the total cost while meeting the demand for each week. Also the order point should be provided.
Primarily, I am looking for readings or tutorial that would help understand how to solve such a problem. It would be great if someone can help with this particular example.
$20,040
while delivery cost for 499 units is$24,950
$\endgroup$Lot-Sizing problem
that is frequently used in the planning and order problem. If the problem data is consisting the row materials and NOT only the end product, using the MILP approach might not be the best one as the inventory balancing constraints satisfying is a complicating task. Instead of using MILP, theMRP heuristic approach
might be interested. $\endgroup$