I am trying to calculate the reorder point and safety stock for a pharmaceutical product. I am using this formula $$r = \mu_{LTD} + z_\alpha\sigma_{LTD}. $$
$$SS = z_\alpha\sigma_{LTD}. $$
where,
$$\mu_{LTD} = \mu_D\mu_L$$
$$\sigma^2_{LTD} = \mu_L\sigma_D^2 + \mu_D^2\sigma_L^2$$
Let's say I take a time granularity of 1 month. That means my calculations for the mean and standard deviations of demand ($\mu_D$ and $\sigma_D$) will be done on a monthly basis. I get these values as $26000$ and $6350$ per month, respectively. The lead time for my product is $\mu_L = 75$ days or $2.5$ months. The standard deviation of lead time is assumed to be 20% of the mean lead time so that $\sigma_L = 0.5$. I also assume a Type 1 service level of 99% to get $z = 2.33$. Putting these values directly in the above formula I get the safety stock as $$SS = 38,000$$ and $$r = 103,000$$
The values I got from the formula seem absurdly high to me. The company typically orders about 25000 units of the product with each order. I will have to place 4 orders just to reach the reorder point and once all of those orders arrive, the amount of inventory I would be holding will be tremendous.
My question: Does the formula mandate that the lead time be shorter than the time granularity considered? Another way I thought about it was that since there are $2$ complete cycles in each lead time period, placing an order $2.5$ months back would be the same as placing it $0.5$ months back, which would yield an effective $\mu_L = 0.5$. I think the second approach should yield some reasonable numbers but I am not sure if it is correct. Any help is appreciated!
EDIT: I thought about this some more and came up with another approach. Suppose I assumed $\mu_L$ to be the "hypothetical lead time" of say $1.5$ months. If I do the calculations taking $\mu_L = 0.5$ (other parameters remaining same), I get $SS = 35,000$ and $r = 74,000$. Since this is a "hypothetical reorder point", I would actually place the order 1 month back. So if the reorder point suggests placing an order on 20th May, I would actually place an order on 20th April. The caveats I can see with this approach are that I would need to forecast the demand well to plan placing orders ahead of time. Again, not sure if this approach is any good.